Proposed Timeline
The Woodlands – 2026 Paint Project
Tentative Timeline
- November 13, 2025: Vendor Selection (COMPLETED – Blue Wave)
- December 11, 2025 – HOA Meeting: Color Choice Selection (COMPLETED – 2 Choices)
- By December 15th: Send out initial pricing details and payment option commitments (COMPLETED)
- January 5, 2026: “Before” drone photoshoot. (COMPLETED)
- January 7, 2026: HOA must obtain formal DCIA approval on paint choices. (COMPLETED)
- By January 31st: Community Vote on color (COMPLETED)
- By February 15, 2026: (COMPLETED)
- Owners must select whether to use Blue Wave or paint themselves
- Payment in full must be collected for those who select Blue Wave.
- February 20, 2026: Logistics Walkthrough
- February 27, 2026: Community-wide landscaping trim.
- February 2026 (Exact Date TBD): Bluewave – PrePaint Inspections
- By February 28, 2026: Final community preparations for paint project commencement
- Owners must remove exterior décor and protect any precious belongings.
- Landscapers will need to trim any flora within 1.5 feet of houses and fences to allow the painter access.
- Final communications to residents regarding the commencement of the paint project.
- March 2026: Blue Wave Paint commencement.
By June 30, 2026: All owners who elected to paint themselves must have their properties completed.
Please click below to go to the permission form!!! Submit before February!!!